Miscellaneous Beneficial Use Pictures
|
 The Boralex power plant. |
 The stockpile of CKD at the Dragon plant in Thomaston.
|
 Dredging sediment.
|
 Mixture of rubber fines, belt wire, and dirt accumulated
underneath a conveyor belt.
|
 A rotating Trommel for sizing tire shreds
|
 Shredding waste tires
|
 Blades for a tire shredding machine
|

Asphalt roofing shingles
|
 Asphalt shingle cold patch product.
|
 Lime mud from the International Paper mill in Jay,
Maine.
|
|
|
|
|
|
|
|
Crushed Sheetrock Gypsum from Commercial Paving and Recycling
|
 A raw sheetrock stockpile.
|
 Ground, unscreened gypsum.
|
 Paper that has been screened out of the crushed
sheetrock.
|
 The final crushed, screened gypsum byproduct.
|
|
|
UMaine Tire Shred Retaining Wall Test Facility
|
 The UMaine retaining wall test facility.
|
 Tire shred backfill in the retaining wall test facility.
|
 Close up view of tire shreds backfilled against the test
retaining wall.
|
 Inside the test facility before tire shreds are added.
|
 Concrete blocks used as surcharge on the tire shred
backfill.
|
 Compacting the tire shred backfill.
|
 The retaining wall test facility with surcharge-loaded
tire shred backfill.
|
|
|
|
Topsham, Maine Tire Shred Projects
|
 Spreading tire shreds for the North Abutment fill in
Topsham, Maine.
|
 Compacting tire shred fill at the North Abutment fill in
Topsham.
|
 Spreading tire chips as backfill against the rigid frame
bridge in Topsham.
|
 Compacting the narrow strip of tire shreds next to the
Topsham bridge. |
 Tire shreds wrapped in geotextiles at the Topsham
bridge.
|
|
|
|
|
|
Portland Jetport Project
|
 Shredding waste tires.
|
 Shredding waste tires.
|
 Shredding waste tires.
|
 Sizing tire shreds.
|
 Waste tires stockpiled and waiting to be shredded.
|
 Site of the Maine Turnpike's Portland Jetport
Interchange prior to construction.
|
 Spreading tire shred fill for the bridge abutments of
the Jetport Interchange.
|
 Unloading tire shreds on top of a layer of geotextiles
at the Portland Jetport exchange.
|
 Portland Jetport Interchange construction.
|
 Tire shreds close-up.
|
|
|
|
|
Richmond, Maine Project
|
|

The test road in Richmond, Maine
|

Delivering a load of tire shreds to the Richmond site
|

Compacting the tire shred layer
|

Spreading a layer of soil on top of the tire shreds
|
|

Geotextiles placed over the tire shreds for one section
of the roadway
|
|
|
|
|
|
UMaine Witter Farm Road Project
|
 UMaine Witter Farm Road in Orono, Maine
|
 Placing tire shreds over a layer of geotextiles.
|
 Spreading tire shred fill in a layer on the Witter Farm
Road.
|
 Paving the Witter Farm Road.
|
|
|
Ashcrete
|
 Ashcrete raw materials
|
 Ashcrete |
 Ashcrete |
 Ashcrete |
 Ashcrete |
 Ashcrete |
|
|
|
|
Searsport Dredge Project
|
 The work site at Mack Point in Searsport. The
dredging equipment is visible, as well as a pile of mixed sediment and
kiln dust.
|
 Dredging is underway.
|
 Dredging is underway.
|
 Close-up of the dredging equipment.
|
 Close-up of the dredging equipment.
|
 A truckload of dredged sediment is dumped onsite.
The material essentially has a moisture content of 100%, and is completely
unworkable.
|
 This pile contains cement kiln dust that was delivered
to the Searsport site from Dragon in Thomaston.
|
 Bucket loads of kiln dust are removed from the pile.
|
 The kiln dust is carried to the pile of sediment that
was previously dumped onsite.
|
 During mixing, the equipment operator also attempts to
remove all pieces of trash from the sediment (i.e. chains, pieces of wood,
metal, etc.)
|
 The sediment and kiln dust are well mixed.
Multiple bucket loads of kiln dust are added. |
 The CKD is completely mixed into the sediment.
|
 The kiln dust is carried to the pile of sediment that
was previously dumped onsite. |
 Piles of previously mixed material are present onsite.
|
 The dredged material and CKD are fully mixed, and piled
near the center of the mixing site. The material already has a
noticeably lower moisture content.
|

This material already set for a day. The moisture content was around
half what it was when it was first dredged.
|
 To further dry the material, it is spread and rotatilled
at another location onsite.
|
 This material has already been rotatilled. After
it sets further, it will be used for construction onsite or at another
site in Bucksport.
|
|
|
|
|