Double Nickel Slide, South Pass, Wyoming
|
|
|
In 1985, a highway alignment
on State Highway 28 in Wyoming initiated a landslide. Rock drains and
berms were installed at the toe of the slide to help stabilize it. In
1993, more movement of the slide was noticed. Figure
1 below shows the slide area.
|
Figure 1. Plan view showing outline of slide area (Dahill, 1994)

|
Measures had to be
taken to stabilize the landslide to prevent further movement and damage. A
combination of four different repair options were used. They are listed
below and shown in figure 2 as well.
-
shift alignment
away from the head of the slide
-
lower the grade to
reduce the slide's driving force
-
create additional
toe berms
-
use a lightweight
fill material like tire shreds
|
Figure 2. Cross section through slide area with slide plane used for
analysis (Dahill, 1994)

|
The tire shred
layer was approximately 6 feet thick, and the fill was placed in 1-ft lifts
compacted with a bulldozer. The tire shred layer was separated from the
soil by geotextiles. Figure 3 shows that the tire shred layer was covered
with 36 inches of subbase aggregate, 12 inches of crushed base aggregate, and 6
inches of pavement.
|
Figure 3. Typical section through pavement and base and subbase courses at
the Double Nickel Slide

|
10,032 c.y. of tire
shreds were used. The material had a unit weight of 35 pcf, and was the
least expensive lightweight fill option at $4/c.y. Approximately 470,000
to 630,000 tires were used in the project.
|
|