Topsham, Maine

Information from Humphrey, 2003
Click here to see photographs of this project
North Abutment Fill

    The north abutment of the Merrymeeting bridge in Topsham was located on soft marine clay.  To increase the factor of safety for the stability of the slope, something had to be done to stabilize the clay or reduce load.  The least expensive option was to excavate some of the abutment slope and replace it with lightweight tire shreds.  Figure 1 shows a cross section of the filled area.

Figure 1. Cross section through North Abutment tire shred fill

Cross section

    To achieve the 14 ft layer of tire shreds that was desired for the project, the layer was overbuilt by 1.5 feet to account for the compressibility of the material.  During placement of the overlying soil, the tire shred fill compressed 14.6 in (370 mm).  In the next 60 days, the fill compressed another 5.3 in (135 mm), and over the following year, another 0.6 in (15 mm) of time dependent settlement occurred.  The total settlement of 10.5 in (520 mm) was 13% greater than the expected settlement of 18 in.  This was due to the fact that time dependent settlement was not accounted for.  The final compressed unit weight of the tire shreds was about 56 pcf, a value very close to the predicted value of 57 pcf.
    Lateral pressures were measured at the completion of tire shred placement (10/3/96) and the completion of soil cover and surcharge placement (10/9/96).  Table 1 gives measured lateral pressures for these dates, as well as for 10/31/96.

Table 1. Summary of lateral pressures on North Abutment Wall

 

PC1-1

PC2-1

PC1-2

PC2-2

PC1-3

PC2-3

Date

Cell elev. = 6.70 m

Cell elev. = 7.77m  

Cell elev. = 8.84 m

10/3/962

7.841

7.41

6.04

7.27

2.62

1.41

10/9/963

17.04

20.04

19.61

30.22

17.05

10.91

10/31/96

18.27

21.05

20.98

32.84

20.24

12.31

1Horizontal pressure in kPa. (kPa x 20.885 = psf)
2Date tire shred placement completed.
3Date soil cover and surcharge placement completed

Rigid Frame Bridge

    A three foot wide strip of tire shreds was used as backfill against a rigid frame bridge in Topsham.  The tire shreds act as a compressible layer that allows movement of the granular borrow, and the development of active earth pressures.  Figure 2 shows the placement of the tire shreds.

Figure 2. Cross section of rigid frame bridge showing location of tire shred zone (Humphrey, et al., 1998)

Cross section

    Figure 3 shows the placement of instruments that were installed to measure pressures, strain, and temperature.

Figure 3. Cross section showing location of instrumentation at station 1004+50 (Humphrey, et al., 1998)

cross section

    Figure 4 gives horizontal stress values measured by pressure cells.  One of the cells (PC1-1) was placed against the granular borrow material.  The data shows that the pressure for the tire shreds was less than half the pressure for the soil.

Figure 4. Horizontal stress as measured by the pressure cells and approximate fill elevation versus date (Humphrey, et al., 1998)

horizontal stress

Figure 5. Comparison of pressures measured on September 1, 1996 (Humphrey, et al., 1998)

pressures

 

Our source links are not currently working.  We apologize for any inconvenience. 

Questions or comments about beneficial use?  Please direct them to a staff member.

 

The University of Maine

ŠThis is an official publication of The University of Maine.  "Beneficial Use of Solid Waste in Maine."

March 12, 2006.  http://useit.umaine.edu/