Portland Jetport

Information from Humphrey, 2003
Click here to see photographs of this project

    A new bridge was constructed over the Maine Turnpike to provide better access to the Portland Jetport.  Approach embankments had to be built on the underlying soft clay found in the area, and measures had to be taken to prevent slope failure.  The existing factor of safety was very low, and different alternatives were considered to reduce the risk of failure.  Tire shreds were chosen to be used as a lightweight fill material in the embankments.  This was the least expensive alternative and didn't impact the surrounding wetlands as stabilizing berms would have.
    Two layers of tire shreds were used.  Each layer was completely surrounded by geotextiles, and the layers were separated by fill material with low permeability.  Guidelines specify that a single layer of tire shred fill should be no more than 10 feet, so two separate layers were necessary to achieve the desired fill thickness of up to 20 feet.  The figure below shows the placement of the fill layers.

Figure 1. Typical embankment section, Portland Jetport

Jetport embankment

    The tire shreds that were used were large in size and fairly uniformly graded.  This resulted in a unit weight of about 49 pcf, which was lower than originally expected.  The tire shred fill experienced rapid compression during loading, but didn't have much time-dependent settlement.  After 5 months, settlement varied from 5 to 21 inches in the upper layer of tire shreds, and from 5 to 8 inches in the lower layer.  The foundation under the embankment settled 2 to 15 inches, accounting for much of the tire shreds' settlement as well.

 

Our source links are not currently working.  We apologize for any inconvenience. 

Questions or comments about beneficial use?  Please direct them to a staff member.

 

The University of Maine

ŠThis is an official publication of The University of Maine.  "Beneficial Use of Solid Waste in Maine."

March 12, 2006.  http://useit.umaine.edu/