Roseburg, Oregon

Information from Humphrey, 2003

    In 1990 and 1991, a tire shred beneficial use project was completed on U.S. Route 42 near Roseburg, Oregon.  As part of a highway improvement project, an embankment was raised, causing the reactivation of an old landslide.  The slide had to be stabilized, and tire shreds were chosen as a lightweight fill material.  These shreds were placed at the head of the slide, and a counter balancing fill was added at the toe of the slide.  Figures 1 and 2 below show the location of the two different fill areas at the site.

Figure 1. Plan view of Oregon tire shred field trial (Upton and Machan, 1993)

Oregon field trial

Figure 2. Cross section through Oregon tire shreds field trail (Upton and Machan, 1993)

Cross section

    Minnesota DOT specifications were followed for the tire shreds:

  • 80% passing the 8-in size

  • 50% larger than the 4-in size

  • maximum size in any direction - 24 in

  • any metal particles had to be contained within the rubber of the shreds

    The shreds were placed in 3-ft lifts, and compacted with a D-8 bulldozer.  The maximum thickness of the compacted tire shred fill was 14 feet, and geotextiles were used at the site to separate these layers of tire shred material from the surrounding soil.
    After the tire shreds were compacted, 36 inches of soil, 23 inches of aggregate base course, and 8 inches of pavement were placed over the fill.  Before these layers were added, the tire shred unit weight was 45 pcf.  After the soil, aggregate, and pavement was added, and compression of the tire shreds occurred, the estimated unit weight was 53 pcf.
    Most of the pavement didn't experience problems with cracking or rutting.  One 50-ft section did require some repair, as a mistake caused the soil cover to be 1 to 1.5 ft thinner than had been specified.  Measured pavement deflections were about 0.25 mm. Figure 3 below gives deflection results.

Figure 3. Deflectometer test data: left, October 30, 1990; middle, January 7, 1991; right, December 12, 1991 (Upton and Machan, 1993)

deflectometer results

    For this project, the cost of the tire shreds was $30/ton, and the placement of the fill cost another $8.33/ton.  The total cost was $27/c.y., minus state subsidy.

 

Our source links are not currently working.  We apologize for any inconvenience. 

Questions or comments about beneficial use?  Please direct them to a staff member.

 

The University of Maine

ŠThis is an official publication of The University of Maine.  "Beneficial Use of Solid Waste in Maine."

March 12, 2006.  http://useit.umaine.edu/